When a fuel distributor received notice that an inactive underground storage tank needed to be permanently closed, removing the tank seemed like the obvious solution. A site inspection changed that plan quickly—the tankhold was located within six inches of an office building foundation.
Rather than risk damaging the structure, Whiterock worked with the Oklahoma Corporation Commission to obtain approval for closure in place.
Once the variance was approved, our team coordinated the required notifications and utility locates, removed the concrete above the tank, disconnected the flow and vent lines, and removed the remaining product and sludge. The tank was filled with water before being safely cut open, then drained and backfilled with compacted fill sand.
After the tank was closed, Whiterock restored the concrete surface, collected the required soil samples using direct-push equipment and submitted them to a certified laboratory. The final step was preparing and submitting the UST closure report to the OCC.
What began as a routine tank closure became a project that required a different approach, careful planning and close attention to both structural and regulatory requirements.
Location: Former Bulk Fuel Facility, Oklahoma
Services: UST Closure, Regulatory Compliance